side the power plant uses an electric motor as equipment to convert electrical energy into mechanical, which uses a 3 phase motor. The Steam Power Plant has FDFan which functions as a device that supplies or forces outside air into the boiler combustion chamber. If the power plant operates, there will certainly be many disruptions which will occur due to several factors. Each motor has its own protection system. Especially on the FDfan 3A motor at the PLTU has several protection systems, including Over Current Relay as protection from overcurrent resulting in short circuit current, then Overload Relay as overload protection. In this report, mathematically analyzing calculations and comparing to determine the starting motor current and pick up current in the relay when under normal conditions or in trip conditions. At the power plant unit 3 FDFan motor with a power of 1722 kW produces a starting motor current of 118 A at the test value and the value of the mathematical calculation of 108.86 A. While the overcurrent relay with a pick up value of 4 A and the value of the mathematical calculation of 4.08 A which can be said to be still relatively normal and in good condition. Overcurrent protection relay is needed on the FDFan motor to prevent overcurrent, it is necessary to adjust the current according to the nameplate so that the motor is working optimally.


Keywords


Motor, Over Current Relay, Protection system

Full Text:

PDF

References


Arief, S., Rahmadino, Y. 2019. Analisa Kapasitas Force Draft Fan Dengan Bahan Bakar Batubara Kualitas Rendah. Power Plant, 4(1):6-11

Arum, S. 2018. Analisis Sistem Proteksi. Yogyakarta: Universitas Muhammadiyah Yogyakarta.

Budi, Y.H., Habibul, I. 2017. Analisa Pengasutan Motor Induksi 3 Fasa 2500 KW Sebagai Penggerak Fan Pada Bag Filter. SINERGI, 21(3): 173-178

Devipriya, P., Sneha, T., Shanmugapriya, P. 2018. Design of Numerical Relay for Over Flux and Over Current Protection in Transformers. Proceeding : International Conference on Computation of Power, Energy, Information and Communication. India. 28-29 Maret 2018.

Dzulqarnain, F. 2015. Prinsip Kerja Siklus Rankine. insinyoer.com. diakses pada tanggal 1 Maret 2020.

Goodall, J.S.H., Chapman, G.S. 1956. An Electronic Over Current Relay for Electrical Machines. Proceedings of the IEE - Part A: Power Engineering, 103(10) : 375-378

Indonesia Power. 2020. Siklus kerja Pembangkit Listrik Tenaga Uap. www. indonesiapower.co.id/id/. diakses pada tanggal 3 Maret 2020.

Istianto, B. R., Wibowo, P. 2017. Analisa dan Optimasi Sistem PLTGU Biomassa Gas Metan dengan Daya 20 MW. Jurnal Teknologi, 9(2): 65-76

Kang, Y.C., Jin, E.S., Kang S.H., Crossley, P.A. 2004. Compensated-current differential relay for protection of transformers. IEE Proceedings - Generation, Transmission and Distribution, 151(3): 281 – 289

Lesita, D., Dedet, C., Dimas, A. 2013. Proteksi Motor Menggunakan Rele Thermal dengan Mempertimbangkan Metode Starting. Jurnal Teknik Pomits, 1(1) : 1-6

Maulana. 2015. Proteksi Motor Induksi 3 Fasa. Palembang: Politeknik Negeri Sriwijaya.

Majid, E., Hamidreza, Z., Hossein, K. K. 2019. Design and Implementation of an Over-Current Relay for the Power Electronic-based Converters Protection. Proceeding : International Conference on Protection and Automation of Power System (IPAPS). Iran. 8-9 Januari 2019.

Stevoelectric. 1993. FREJA300 Relay Test System. Sydney: Megger.com. Diakses 1 maret 2020.

Valyakala, A. M., Dileeplal, J., & Paul, B. 2013. Root Cause Analysis for the Failure of a Forced Draft Fan. International Journal of Engineering Research and Development, 6(5) : 84-90

Sung, H. L., Seung, T.L. 2019. Analysis on Coordination of Over-Current Relay Using Voltage Component in a Power Distribution System With a SFCL. IEEE Transactions on Applied Superconductivity, 29 (5).

Supersedes, I.L. 1997. Type CO-5 Step Time Overcurrent Relay. Florida: library.e.abb.com. Diakses 1 maret 2020.

Suwanda, Teguh F. 2015. Overcurrent Relay Pada Motor GA-4101C-M Cooling Water Pump di PT. Chandra Asri Petrochemical, Tbk. Jurusan Teknik Elektro,Universitas Ageng Tirtayasa.

Valyakala, A. M., Dileeplal, J., & Paul, B. 2013. Root Cause Analysis for the Failure of a Forced Draft Fan. International Journal of Engineering Research and Development, 6(5) : 84-90

Voloshin, E.A., Voloshin, A. A., Usachev, S. S., Ententeev, A.R., Maksudov, B.T., Livshits, S.A. 2018. Increase of Efficiency of Relay Protection Reliability in Modes with Deep Saturation of Current Transformers Using The Methodology Based on The Application of Artificial Neural Networks. Proceeding : International Youth Scientific and Technical Conference Relay Protection and Automation. Russia. 27-28 September 2018.

Yoyok, T., Ontoseno, P., Sjamsjul A. 2013. Analisis Studi Rele Pengaman (Over Current Relay Dan Ground Fault Relay) pada Pemakaian Distribusi Daya Sendiri dari PLTU Rembang. JURNAL TEKNIK POMITS, 2(2) : 159-164




DOI: https://doi.org/10.24853/jurtek.13.1.55-62

Refbacks

  • There are currently no refbacks.


Jurnal Teknologi Indexed by:

Directory of Open Access JournalGoogle ScholarRoadIndonesia Scientific Journal Database (ISJD)Index Copernicus International (ICI)Garba Rujukan Digital(Garuda)CrossrefScience and Technology Index (SINTA)Directory of Research Journal Indexing (DRJI)CiteFactorResearchgateIndonesia One SearchAcedemia.eduResearchBibAcademickeysBielefeld Academic Search Engine (BASE)JifactorPKP IndexSherpa romeoworldcat


Copyright of Jurnal Teknologi (e-ISSN:2460-0288, p-ISSN:2085-1669).

 

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License

Powered by Puskom-UMJ